Week 14: Technical Paper Submission and Completing Thesis

Image
  Date : 9/1/2022  –  13/1/2022 Activity :  Technical Paper submission and completing Thesis Purpose :    To finalize technical paper and updating thesis on every chapter. Procedure : 

Week 13: Presentation and Demonstration Day

Image
Date :  2/1/2022  –  6/1/2022 Activity :  Presentation and demonstration day Purpose :    To present prototype and project development Procedure : 

Week 12: Preparation for Exhibition Day

Image
  Date :  26/12/2022  –  30/12/2022 Activity :  Preparation for Exhibition Day Purpose :    To  make preparation before Presentation Day Procedure : 

Week 11: Troubleshoot project and build prototype

Image
Date :  19/12/2022  –  23/12/2022 Activity :  Troubleshoot project and build prototype Purpose :    To accomplish project and prototype. Procedure : 

Week 10: Meeting with Supervisor

Image
Date : 12/12/2022  –  16/12/2022 Activity :  Meet with Supervisor Purpose :    To receive consultation regarding working progress. Procedure : 

Week 9: Focus on Completing Content in Thesis

Image
Date :  28/11/2022  –  2/12/2022 Activity :  Focus on completing content in thesis Purpose :  To update thesis and change the project  flowchart Procedure :

Week 8: Collecting data of geolocation

Image
   Date :  28/11/2022  –  2/12/2022 Activity :  Collecting geolocation data Purpose :  To collect data of detected location Procedure :

Week 7: Construct Wiring the Circuit

Image
  Date :  14/11/2022  –  18/11/2022 Activity :  Construct circuit wiring Purpose :  To combine and construct the circuit for both wireless communication lines. Procedure :

Week 6: Deployment of Software III

Image
Date :  7/11/2022  –  11/11/2022 Activity :  Deployment of Software III Purpose :  To create Home Page link to Google Maps Procedure :

Week 5: Deployment of Software II

Image
Date :  31/10/2022  –  4/11/2022 Activity :  Deployment of Software II Purpose :  To solve the issues on creating Android application Procedure :

Week 4: Deployment of Software I

Image
  Date : 24/10/2022  –  28/10/2022 Activity :  Deployment of software Purpose :  To learn on how to develop an Android application for this project Procedure : Understanding the deployment of software

Week 3: Testing the capability of LoRa

Image
Date :  17/10/2022  –  21/10/2022 Activity :  Testing the capability of LoRa Purpose :  To test the capability of hardware Procedure :

Week 2: Purchase Components

Image
Date :  10/10/2022  –  14/10/2022 Activity :  Purchase components Purpose :  To purchase components Procedure : 

Week 1: Revised Components Implementation

Image
  Date :  03/10/2022 –  07/10/2022 Activity :  Revised Components Implementation Purpose :  To make changes of hardware implementation Procedure :